AsBuilt for a Hydrocyclone Replacement

Laser scanning, 3D modeling, and structural design for hydrocyclone replacement at a power plant, delivering accurate as-built data and seamless piping integration.

The Challenge

AsBuilt was contracted by a power generation facility to support a Hydrocyclone replacement project intended to improve the reliability and performance of the plant’s dewatering system.

The existing hydrocyclone and support structure required replacement to accommodate a new unit with updated loading requirements, revised piping connections, and modified elevations. The project required:

  • Accurate existing-condition documentation
  • Structural analysis for new equipment loading
  • Proper alignment of supply and discharge piping
  • Seamless integration with the active dewatering system
  • Reduced installation risk within an operating plant

Incomplete legacy drawings and undocumented field changes increased the risk of misalignment, structural conflicts, and installation delays.

The Solution

Laser Scanning & Data Validation

AsBuilt conducted a high-resolution terrestrial laser scan (LiDAR) of the hydrocyclone and surrounding mechanical area. The scan captured:

  • Existing hydrocyclone geometry
  • Structural steel supports and framing
  • Adjacent piping and tie-in points
  • Utilities and nearby equipment
  • Elevation relationships and spatial constraints

The scan data was registered, post-processed, and quality-checked to ensure engineering-grade accuracy before being prepared for modeling.

3D Modeling & Structural Redesign

Using the verified point cloud data, AsBuilt developed a precise 3D as-built model (DWG format) of the existing structure and piping systems. Based on the model:

  • A new support structure was engineered to accommodate the updated hydrocyclone
  • Structural members were sized and positioned to meet revised loading requirements
  • Elevations were adjusted to align with the new equipment footprint
  • Clash detection was performed to prevent interferences

The redesigned structure ensured proper support, access, and long-term operational stability.

Piping Design & Integration

To integrate the new hydrocyclone into the dewatering system, AsBuilt developed detailed supply and discharge piping drawings, including:

  • Tie-in locations to existing piping
  • Revised routing and elevations
  • Connection details for fabrication and installation

This ensured accurate fitment and minimized field modifications during installation.

Deliverables

  • Raw laser scan data (Recap format)
  • Post-processed, registered point cloud
  • Photorealistic 3D visualization
  • 3D as-built model (DWG)
  • Structural design for new hydrocyclone support
  • Supply and discharge piping drawings

Results & Impact

The project delivered a fully engineered hydrocyclone replacement solution grounded in accurate as-built data. By combining laser scanning, structural design, and piping integration, AsBuilt reduced installation risk, improved dewatering system reliability, and ensured seamless integration within the existing power plant infrastructure.

‍